A KSA luxury hotel pre-opening has 24 months between groundbreaking and grand opening. IT integration must complete every system, every integration, every test, every staff training before key handover. There is no “we’ll fix it after opening” — opening either happens with working IT or doesn’t happen.
Here’s what 24 months actually looks like.
T-24 to T-18: Concept and design
Brand selected, owner-operator agreements signed, schematic design progresses. IT consultant engaged. BIM model started. Brand standards translated into engineering specifications.
IT scope at this phase: design participation, BIM coordination, brand-standards interpretation. Most procurement happens later.
T-18 to T-12: Detailed design and procurement
Detailed design completes. Brand standards confirmed. PMS choice locked (Opera Cloud, Protel, IDS, or Mews). Vendor selections finalized for IPTV, GRMS, phones, AV, networking.
Long-lead procurement begins now: PBX equipment, IPTV servers, Crestron control systems, structured cabling materials. Saudi Customs lead times factored.
T-12 to T-9: Back-of-house cabling
Structured cabling installation begins back-of-house first: kitchen, F&B, executive offices, IT room, MEP rooms. Front-of-house and guest rooms wait for finishing trades.
IDF rooms commissioned. IT room rough-in complete.
T-9 to T-6: Guest room infrastructure
Guest room cabling, GRMS wiring, IPTV cabling. Coordinated with FF&E (furniture, fixtures, equipment) procurement so bedside USB ports and work-surface outlets land in correct positions.
PMS installation begins. Configuration takes weeks, not days.
T-6 to T-4: Systems integration
PMS-IPTV integration tested. PMS-phone integration via HSIM. PMS-locks integration. PMS-POS integration. GRMS scenes programmed. Wi-Fi rolled out and tuned.
Each integration tested individually before integration testing.
T-4 to T-3: Full integration testing
End-to-end scenarios tested: simulated check-in flowing through PMS to phone-name display, IPTV welcome screen, GRMS welcome scene, lock activation. Edge cases tested: room moves, wrong-language guests, late check-out.
T-3 to T-2: Operational dress rehearsal
Full simulation with hotel staff. Real check-in, real F&B service, real housekeeping rotation, real wake-up calls. Defects identified and fixed.
T-2 to T-1: Staff training and final tuning
Front desk, housekeeping, F&B, IT, security all trained on technology. Soft opening preparation. Final defect resolution.
T-1 to T-0: Soft opening
Limited operations, real (paying or invited) guests. Real feedback drives final tuning.
T-0: Grand opening
Full operations. The 24 months either delivered on time or didn’t. There is no middle ground.
What slips most often
PMS choice locked too late (T-9 instead of T-15). Long-lead items arrive too late. Brand standards revision mid-project. Site readiness slip from general contractor compresses IT into impossible window.
The discipline that prevents these slips is upfront commitment, weekly governance, and a project manager who fights for IT scope at every coordination meeting.
→ Hotel Pre-Opening service → | PMS Integration → | Hotel Phones →